Key facts
- Seattle Parks and Recreation and the Seattle Department of Transportation are building a new sidewalk along the east side.1
- The dirt path will close on November 23 for preparatory groundwork, City of Seattle said.1
- Concrete construction will begin in early December, City of Seattle said.1
- The concrete construction phase is estimated at 2-3 weeks, City of Seattle said.1
Seattle Parks and Recreation and the Seattle Department of Transportation are building a new sidewalk along the east side of Lake Washington Boulevard near South Adams Street, the City of Seattle said.1
The new sidewalk will connect to the paved Lake Washington Boulevard Trail, the City of Seattle said.1
The new sidewalk will be built by SDOT crews thanks to funding from the voter-approved Seattle Transportation Levy, the City of Seattle said.1
What the new sidewalk will do
The 330-foot-long sidewalk will follow an existing “desire” footpath where the grass has been visibly affected by many people walking over the years, the City of Seattle said.1
In some places the new sidewalk will slightly differ from the beaten path to preserve trees and avoid erosion, the City of Seattle said.1
The new sidewalk will fill a gap in the Lake Washington Boulevard Trail where the current paved path veers east into a parking lot, the City of Seattle said.1
Once complete, the new sidewalk will become part of the Lake Washington Boulevard Trail providing a continuation of paved access for neighbors entering South Adams Street, the City of Seattle said.1
The new sidewalk will provide an accessible pedestrian bypass of the Adams Street Boat Launch for runners, walkers, and rollers traveling the length of the Lake Washington Boulevard Trail, the City of Seattle said.1
Construction schedule and detours
The dirt path will close on November 23 for preparatory groundwork, and pedestrian detour signs will be placed along an accessible route, the City of Seattle said.1
Concrete construction will begin in early December and may last through the end of December, the City of Seattle said.1
This phase is estimated at 2-3 weeks, but the exact duration of construction depends on the weather and other factors, the City of Seattle said.1
During the concrete construction phase, one lane of Lake Washington Boulevard will need to be closed intermittently, and SDOT crews will be directing traffic during these times, the City of Seattle said.1
This phase will not disrupt vehicle traffic, the City of Seattle said.1
Trees and future work
Three recently planted trees will be safely transplanted outside the work area by Seattle Park and Recreation Arborists, the City of Seattle said.1
In 2027, work will continue including paving improvements to the Lake Washington Boulevard Trail and additional safety improvements to the Lake Washington Boulevard roadway, the City of Seattle said.1
This project is funded by the 2024 Seattle Transportation Levy and part of SDOT’s New Sidewalks & Walkways Program which is building 350 blocks of new pathways citywide by the end of 2032, the City of Seattle said.1